EnglishEU Energy Law & Litigation7 min readNovember 6, 2026

Nord Stream 2 AG v European Parliament and Council: the Court of Justice rules on the appeal in Case C-118/25 P

An analysis of the judgment of the Court of Justice of the European Union (Eighth Chamber) of 5 November 2026 in Case C-118/25 P, examining the appeal brought by Nord Stream 2 AG against the European Parliament and the Council of the European Union concerning Directive (EU) 2019/692 on the internal market in natural gas.

Introduction

On 5 November 2026, the Court of Justice of the European Union, sitting as the Eighth Chamber, delivered its judgment in Case C-118/25 P, Nord Stream 2 AG v European Parliament and Council of the European Union. The case concerns an appeal brought by Nord Stream 2 AG challenging an earlier judicial decision related to Directive (EU) 2019/692, which governs the internal market in natural gas within the European Union.

This judgment is situated within a broader and well-documented line of litigation involving Nord Stream 2 AG and the EU institutions, most notably the prior judgment of 12 July 2022 in Case C-348/20 P (Nord Stream 2 v Parliament and Council, EU:C:2022:548). The present appeal raises a series of procedural and substantive questions that the Court was called upon to address, including issues of admissibility, alleged errors of law, distortion of facts and evidence, procedural measures, and misuse of powers.

Background and legislative context

Directive (EU) 2019/692 forms the central legislative instrument at issue in this litigation. The directive concerns the internal market in natural gas and was adopted by the European Parliament and the Council of the European Union. Nord Stream 2 AG, as an entity directly affected by the regulatory framework established by that directive, has been engaged in legal proceedings before the EU courts seeking to challenge the application of that instrument.

The litigation history is significant. The Court of Justice had already ruled in the matter in its judgment of 12 July 2022 in Case C-348/20 P. The present case, C-118/25 P, represents a further stage in the appellate proceedings, with Nord Stream 2 AG continuing to contest the legal and factual basis of the decisions made against it. The involvement of the second paragraph of Article 61 of the Statute of the Court of Justice of the European Union is also noted in the case, indicating that the procedural framework governing the referral or continuation of the case before the Court was itself a matter of consideration.

Grounds of appeal raised by Nord Stream 2 AG

According to the document, Nord Stream 2 AG advanced several distinct grounds of appeal before the Eighth Chamber. These grounds, as identified in the judgment, encompass the following categories: admissibility, alleged errors of law, distortion of the facts and evidence, measures of inquiry and of organisation of the procedure, and misuse of powers.

The admissibility ground is a threshold question that the Court was required to address before examining the substance of the appeal. Questions of admissibility in EU appellate proceedings are governed by the Statute of the Court of Justice and the Rules of Procedure, and their resolution can determine whether the Court proceeds to examine the merits of the case at all.

The ground relating to errors of law is a standard basis for appeal before the Court of Justice, which, in its appellate jurisdiction, reviews points of law rather than reassessing the facts as found by the General Court. The allegation of distortion of facts and evidence is a recognised, though exceptional, ground of appeal, permitting the Court of Justice to intervene where the lower court has manifestly misread the material before it.

The grounds concerning measures of inquiry and of organisation of the procedure relate to the conduct of the proceedings before the lower court, while the allegation of misuse of powers — a concept with a specific meaning in EU law — suggests that Nord Stream 2 AG contended that powers were exercised for purposes other than those for which they were conferred.

The role of Article 61 of the Statute of the Court of Justice

The document specifically references the second paragraph of Article 61 of the Statute of the Court of Justice of the European Union as a relevant provision in this appeal. Article 61 of the Statute governs the powers of the Court of Justice when it sets aside a decision of the General Court, including the conditions under which the Court may itself give final judgment in the matter or refer the case back to the General Court.

The invocation of this provision in the context of Case C-118/25 P underscores the procedural complexity of the litigation and the need to determine the appropriate course of action following any finding by the Court of Justice on the grounds of appeal advanced by Nord Stream 2 AG.

Significance of the prior judgment of 12 July 2022

The document expressly references the judgment of 12 July 2022 in Case C-348/20 P (Nord Stream 2 v Parliament and Council, EU:C:2022:548) as part of the procedural and legal framework of the present appeal. This prior ruling by the Court of Justice is directly relevant to understanding the trajectory of the litigation and the issues that remained to be resolved in Case C-118/25 P.

The explicit citation of the 2022 judgment within the metadata of the present case indicates that the earlier ruling forms part of the legal backdrop against which the Eighth Chamber assessed the grounds of appeal in the 2026 proceedings. Readers seeking to understand the full context of the present judgment should consult the 2022 ruling as identified in the official document.

Institutional parties and the appellate structure

The respondents in Case C-118/25 P are the European Parliament and the Council of the European Union, the two co-legislators responsible for the adoption of Directive (EU) 2019/692. Their position as defendants in this litigation reflects the nature of the challenge brought by Nord Stream 2 AG, which targets the legislative act itself and its application to the appellant's situation.

The case was heard by the Eighth Chamber of the Court of Justice, which is one of the chambers to which cases are assigned in accordance with the Court's internal rules. The composition and assignment of chambers is a matter of the Court's procedural organisation and does not affect the binding character of the judgment delivered.

Conclusion

The judgment of 5 November 2026 in Case C-118/25 P, Nord Stream 2 AG v European Parliament and Council of the European Union, represents a significant development in the ongoing litigation concerning Directive (EU) 2019/692 and the internal market in natural gas. The Eighth Chamber of the Court of Justice was called upon to rule on a range of grounds of appeal, including admissibility, errors of law, distortion of facts and evidence, procedural measures, and misuse of powers, within the framework established by the Statute of the Court of Justice and the prior judgment of 12 July 2022.

This judgment contributes to the body of EU case law on the internal energy market and on the procedural rules governing appeals before the Court of Justice. Practitioners and academics working in the fields of EU energy law, administrative law, and EU litigation procedure will find the case of relevance to their understanding of how the Court approaches these categories of legal challenge.

This article is for educational and informational purposes only and does not constitute legal advice.

Sources consulted

Published by Synojus International

Back to English publications
SYNOJUS SERVIÇOS TECNOLÓGICOS LTDA · CNPJ 66.267.091/0001-34 · Rua Pernambuco, 364, Nova Imperatriz, Imperatriz/MA, CEP 65.907-270 · contato@synojus.com.br